Non-Compliance detail


  
Summary
 
Licence number: 1802
Annual Return Start: 01 Jun 2010
Annual Return End: 31 May 2011
Date Received: 22 Jul 2011
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
P1.3 The existing flow meter at EPA point 10 has failed. Alternative calculation method has been utilised. Installed a FloDar but was unsuccessful. Currently in consultation with equipment supplier to rectify problems. Appropriate Action taken by licensee 1
L2.1 Nitrogen & Oil & Grease load limit exceeded. New dewatering facility constructed. Aeration upgrade underway. Appropriate Action taken by licensee 1